Leave Your Message
News Categories

Key Points for the Installation of Two Post Lift

2022-07-01

To ensure the safety and stability of lifting equipment installation, the following detailed operation specifications and precautions are provided, covering from foundation confirmation and work position planning to final debugging and operation:

I. Foundation Confirmation Before Installation

Core Objective: Avoid equipment tilting, abnormal noise, or even overturning caused by insufficient foundation strength.

Concrete Curing and Strength Requirements

  • Double-column with 4.5 tons and below: Concrete strength ≥ C25, thickness ≥ 200mm, curing period ≥ 20 days.
  • 5-6 tons double-column: Concrete strength ≥ C30, thickness ≥ 250mm, curing period ≥ 20 days.
  • 8 tons double-column: Concrete strength ≥ C30-C35, thickness ≥ 400mm, curing period ≥ 20 days.

Horizontal Error and Installation Requirements

  • Relative horizontal error of the installation positions of the two columns on the ground < 5mm.
  • The base plate of the lifting machine must directly contact the concrete foundation to ensure load stability.


II. Work Position Size Planning

Standard Size

         It is recommended to reserve (7000-8000) mm × 4000 mm according to the 4S standard work position.

Space Requirements

  • Ensure that the vehicle can drive onto and off the lifting machine smoothly.
  • If the roof is low, install a light-blocking alarm device on the ceiling to prevent the lifted vehicle from colliding with the roof.

III. Power Supply and Air Source Access

Power Supply Specifications

  • Three-phase core wire ≥ 2.5mm², single-phase core wire ≥ 4mm².
  • The power supply should be reserved 1.5 meters from the ground to the main column.
  • If the formal power supply is not connected before installation, prepare a 380V three-phase four-wire temporary power supply for equipment debugging and training.

Space Height

  • The roof height for gantry lifting machines should reach 4 meters, and that for floor lifting machines should reach 3.5 meters.

IV. ​​​​​​​Preparation of Installation Tools and Materials

  • Hydraulic Oil: Prepare 13 liters of L-HM46 anti-wear hydraulic oil for each double-column lifting machine.
  • Auxiliary EquipmentPrepare a forklift of more than 2T for loading, unloading, moving, and installation operations.
  • NoteThe detailed list of installation equipment and tools shall be subject to the information provided by the lifting machine manufacturer.

V. Erecting Columns and Confirming Dimensions

  • Gantry Lifting Machine: Splice the crossbeam on the ground, connect the oil pipe, wires, and steel wire rope through the crossbeam, and then erect the two columns.
  • Floor Double-column Lifting MachineDirectly erect the columns and confirm the dimensions.
  • Position RequirementsThe distance from the wall to the floor position of the lifting machine is not less than 3 meters, and adjust the middle dimension of the two columns according to the equipment model.

VI.Fixing Expansion Bolts and Adjusting Column Verticality

  • Drilling and Cleaning: Select a drill bit according to the size of the expansion bolt, the drilling depth should be consistent with the length of the expansion bolt, and clean the dust.
  • Vertical CalibrationUse a plumb bob to measure the verticality of the column, adjust it, and then tighten the expansion bolts.

VII.​​​​​​​Fixing the Pump Station, Wiring Connection, and Installing Lifting Arms

  • Pump Station and Control Box InstallationFix the pump station and control box on the column.
  • Wiring ConnectionConnect the limit switch, motor cable, and other wires to the control box.
  • Hydraulic Oil FillingAdd No. 46 anti-wear hydraulic oil to the pump station oil tank.
  • Lifting Arm InstallationThe short arm should be close to the front of the vehicle to ensure the correct installation direction.

VIII.Connecting External Power Supply and Debugging the Lifting Machine

Power Supply Connection

Connect the power cord of the control box to the external power supply.

Exhaust and Trial Operation

  • Operate the up button to raise the lifting machine by 400mm. For inverted top cylinders, unscrew the upper exhaust hole to discharge air, then tighten it (positive top cylinders do not need exhaust).
  • Lower to the lowest position, tighten the steel wire rope, and check the synchronization of the two-column safety locks.

Load Test

Raise the vehicle to the highest position and lock it, ensuring that the distance between the lock position and the upper limit is 3 centimeters.

IX.​​​​​​​Inspection and Maintenance Before Operation

  • Lubrication TreatmentApply butter to the steel wire rope and lubricating oil to the slideway.
  • Seal CheckTighten all oil pipe joints and fixing screws to avoid oil leakage or looseness.
Operators must receive safety specification operation training before taking up their posts.
For any questions about installation, please call the customer service hotline +86-10-52478890/1/2/3 or contact the local dealer.